New Town Primary School: Laminate Through a Term Break
Nine hundred square metres of commercial laminate through corridors and classrooms in a two-week term break.
- Project Category
- Commercial Education
- Location
- New Town, TAS
- Material Selection
- AC5 Commercial Laminate
- Installation Time
- 12 Days
The Challenge & Vision
Two weeks, no extensions, and 900 square metres across nine classrooms and the main corridor spine. Term dates do not move. The floor also had to meet the department's slip rating for a school corridor and survive a decade of trolleys, chairs and a great deal of running.


The Solution
Two crews worked from opposite ends of the corridor spine and met in the middle on day eight, with classrooms completed in parallel behind them. We specified AC5 commercial laminate — the grade above what a school brief usually calls for — because the replacement cost of a second term-break shutdown dwarfs the material difference.
- Total Area
- 900m²
- Total Area
- Delivered In
- 12 Days
- Delivered In
Specified Above the Brief
AC5 Commercial
A grade above the brief, because a second shutdown costs more than the material.
Slip Rated
Meets the department's corridor requirement in both dry and wet states.
Two Crews
Parallel working is what turned a three-week job into a twelve-day one.
Project Details
- Client
- New Town Primary School
- Location
- New Town, TAS
- Total Area
- 900 sqm
- Timeline
- 12 Days in a Term Break
- Material
- AC5 Commercial Laminate
Project Roadmap
Twelve working days inside a fourteen-day term break, with two days in hand.
Day 1: Audit
Slab moisture tested across all nine classrooms and the corridor spine.
Day 2–3: Prep
Old vinyl lifted, slab ground and levelled ahead of the two crews.
Day 4–10: Fit
Corridor worked from both ends inward, classrooms completed in parallel.
Day 11–12: Handover
Trims fitted, full clean, and sign-off two days before students returned.
View Next Project
Bridgewater Rental PortfolioInspired by this project?
Tell us about your space and we will walk you through the options, the timeline and the cost.